NEW QUESTION 40
What can programme leaders do to influence key stakeholders?

  • A. Analyze stakeholder influence and interest
  • B. Produce a stakeholder map to show areas of interest
  • C. Hold visioning workshops to draft the vision statement
  • D. Create a programme communications plan

Answer: D

 

NEW QUESTION 41
Which is the BEST definition of a stakeholder?

  • A. A member of the programme management team or project management team
  • B. An individual, group or organization that can affect, or be affected by a programme
  • C. A member of a team that is formed to help its operational area through the change cycle
  • D. An individual accountable for the success of the programme

Answer: B

 

NEW QUESTION 42
Which is a feature of an effective programme organization?

  • A. Monitored and controlled programme changes
  • B. A business case agreed by the stakeholders
  • C. A quality assured configuration management system
  • D. Clear accountability for each management role

Answer: A

 

NEW QUESTION 43
Which document informs and directs identifying a Programme and Defining a Programme?

  • A. Programme Brief
  • B. Programme Mandate
  • C. Programme Preparation Plan
  • D. Programme Blueprint

Answer: A

 

NEW QUESTION 44
Which of the following statements about the business change manager role are true?
1. It provides a bridge between the programme and business operations
2. It delivers the new capability to business operations

  • A. Neither 1 or 2 is true
  • B. Only 2 is true
  • C. Both 1 and 2 are true
  • D. Only 1 is true

Answer: D

 

NEW QUESTION 45
Which role is responsible for delivering the capability?

  • A. Programme manager
  • B. Business change manager
  • C. Senior responsible owner
  • D. Programme board

Answer: C

 

NEW QUESTION 46
What document provides terms of reference for the Sponsoring Group?

  • A. Programme Brief
  • B. Quality and Assurance Strategy
  • C. Resource Management Plan
  • D. Organization Structure

Answer: D

 

NEW QUESTION 47
Which describes an impact of a risk?

  • A. Possibility that something will go wrong
  • B. An event that might increase a programme's outcome
  • C. The amount of risk that will be tolerated
  • D. Effect on the programme if something goes wrong

Answer: D

 

NEW QUESTION 48
Which of the following statements about business change and transition costs in the business case are true?
1. Include the costs of any interim operational resources required to embed the change.
2. Include the costs of a contingency budget for dealing with risk.

  • A. Neither 1 and 2 are true
  • B. Only 2 is true
  • C. Both 1 and 2 are true
  • D. Only 1 is true

Answer: D

 

NEW QUESTION 49
Which is a trigger for a compliance programme?

  • A. The organization has to change to meet requirements of new legislation
  • B. The corporate board has created a vision for change
  • C. A number of stand-alone projects would benefit from better coordination
  • D. The organization chooses to take a new innovative approach to product development

Answer: A

 

NEW QUESTION 50
What is the BEST reason for using programme management?

  • A. It concentrates on delivering outputs
  • B. It removes the need for strong leadership
  • C. It provides a vision for the entire organization
  • D. It enables stakeholder engagement

Answer: A

 

NEW QUESTION 51
Which transformational flow process results in the achievement of outcomes?

  • A. Realizing the Benefits
  • B. Managing the Tranches
  • C. Delivering the Capability
  • D. Closing a Programme

Answer: A

 

NEW QUESTION 52
What role authorizes improvements to the wording of the Vision Statement in order to provide greater clarity for stakeholders?

  • A. Programme Assurance
  • B. Senior Responsible Owner
  • C. Business Change Manager
  • D. Programme Manager

Answer: B

 

NEW QUESTION 53
Which document is updated throughout the programme when new information on benefits and risks becomes available?

  • A. Programme Brief
  • B. Information Management Plan
  • C. Business Case
  • D. Benefits Management Strategy

Answer: B

 

NEW QUESTION 54
Which risk response encourages collaboration on risk management activities?

  • A. Prepare contingent plans
  • B. Reduce
  • C. Share
  • D. Avoid

Answer: C

 

NEW QUESTION 55
Which role facilitates assessments of the impact of changes on the target operating model?

  • A. Senior responsible owner
  • B. Programme manager
  • C. Business change manager
  • D. Programme office

Answer: D

 

NEW QUESTION 56
Which of the following statements about a vision-led programme is true?
1. Tends to be top down in approach, with cross functional implications
2. Evolves from concurrent projects

  • A. Neither 1 or 2 is true
  • B. Only 2 is true
  • C. Both 1 and 2 are true
  • D. Only 1 is true

Answer: D

 

NEW QUESTION 57
Which is NOT a characteristic of the programme management principles?

  • A. They enable practitioners to achieve transformational change
  • B. They have been successful when applied in practice
  • C. They ensure practitioners follow common procedures
  • D. They are valid in all programme management contexts

Answer: D

 

NEW QUESTION 58
Which area of management within programme quality tracks and protects project outputs?

  • A. Supply chain
  • B. Information
  • C. Process
  • D. Asset

Answer: D

 

NEW QUESTION 59
Which is a transformational flow process?

  • A. Reviewing Benefits
  • B. Realizing the Benefits
  • C. Benefits Profiling
  • D. Benefits Management

Answer: B

 

NEW QUESTION 60
Which is MOST likely to lead to the re-definition and re-scoping of a programme?

  • A. Redefined programme management strategies
  • B. Reorganized Programme Office
  • C. Changed corporate strategies
  • D. Updated programme team experience

Answer: B

 

NEW QUESTION 61
Which role would be MOST LIKELY to initiate assurance reviews of project performance?

  • A. Programme manager
  • B. Senior responsible owner
  • C. Business change manager
  • D. Programme office

Answer: A

 

NEW QUESTION 62
......

Exam Questions and Answers for  MSP-Foundation Study Guide Questions and Answers!: https://www.prepawaypdf.com/MSP-Foundation/MSP-Foundation-practice-exam-dumps.html