PMI-200 PDF Pass Leader, PMI-200 Latest Real Test [Q25-Q41]

Share

PMI-200 PDF Pass Leader, PMI-200 Latest Real Test

Valid PMI-200 Test Answers & PMI-200 Exam PDF


PMI PMI-200 Exam Syllabus Topics:

TopicDetails
Topic 1
  • Enhance creativitybyexperimentingwith new techniques and process ideas
  • Establish collaborative behaviors among the members of the organization
Topic 2
  • Continuously identify and prioritize the environmental, operational
  • Provide transparency regardingworkstatus by communicating team progress,work quality, impediments
Topic 3
  • Help ensure that everyone has a common understanding of the values and principles of agile
  • Elicit and prioritize relevant non-functional requirements
Topic 4
  • Support change at the system or organization levelby educating the organization and influencing processes
  • Limit increment size and increase review frequencywith appropriate stakeholders
Topic 5
  • Establish stakeholder relationships by forming a working agreement among key stakeholders
  • Define deliverables by identifying units that can be produced incrementally in order to maximize their value to stakeholders
Topic 6
  • Reduce distractions in order to establish a predictable outcome and optimize the value delivered
  • Refine requirements by gaining consensus on the acceptance criteria for features

 

NEW QUESTION 25
A development team has finished identifying the tasks they will be accountable for during the next sprint.Which of the following tools best provides transparency into the progress throughout the sprint?

  • A. Gantt chart
  • B. Burndown chart
  • C. Management baseline chart
  • D. Hours expended chart

Answer: B

 

NEW QUESTION 26
Agile project development processes typically:

  • A. Document each business process individually and in detail.
  • B. Use a Gantt chart with well-defined activities, responsibilities, and time frames.
  • C. Map the iteration backlog to a Work Breakdown Structure (WBS).
  • D. Encapsulate analysis, design, code, and test within an iteration.

Answer: D

 

NEW QUESTION 27
The best approach to estimate the work on a project when using story points is to have:

  • A. Team members assign estimates by averaging Planning Poker cards.
  • B. Two or three senior team members estimate and take the average of their times.
  • C. The team work together to agree on estimates in a group setting.
  • D. The most senior team member prepare the estimates.

Answer: C

 

NEW QUESTION 28
Which of the following would be most likely to assist when a customer has difficulty prioritizing stories?

  • A. Have the team provide guidance into where their priorities lie to the customer.
  • B. Have the team rewrite the stories with additional details to clarify requirements.
  • C. Provide additional technical details to give the customer insight into technical challenges.
  • D. Split the stories into smaller ones to allow the customer to choose the pieces that they want.

Answer: D

 

NEW QUESTION 29
Which are some of the most important benefits of an Agile team sitting together in a colocated, open environment?

  • A. Costs are reduced as the need for conference rooms decreases, and the team can keep track of where members are more accurately.
  • B. Communication is improved; wait-time and rework are reduced; barriers between groups break down, and groups gain respect for each other professionally.
  • C. Osmotic communication is reduced; space is used more efficiently; groups work together more effectively, and team dynamics are improved.
  • D. Team members can be held more accountable for their time and effort, and pair programming is easier as people have less distance to move to sit with their partner.

Answer: B

 

NEW QUESTION 30
Which of the following is critical for the success of distributed Agile teams?

  • A. Shared knowledge
  • B. High volume of communication
  • C. Cost containment
  • D. Culture of collaboration

Answer: D

 

NEW QUESTION 31
In a Lean project environment, visual controls:

  • A. Are helpful while the team is forming but are less important for more experienced teams.
  • B. Are easy to use, reflect the team's progress, and show the team what to do next.
  • C. Should be kept to a minimum to avoid distracting the team from high-value activities.
  • D. Can be used by management for communicating specific corrective direction.

Answer: D

 

NEW QUESTION 32
The most appropriate model for a geographically distributed project team is one in which the team is distributed across:

  • A. many locations, with relatively few people at each location developing and testing decoupled subsystems.
  • B. relatively few locations, with each location team comprised of a complete development group developing decoupled subsystems.
  • C. relatively few locations, and tasks are divided along functional lines with design in one location, coding in another, and testing in another.
  • D. locations in the same time zone, working on the same systems while leveraging rich communication channels.

Answer: B

 

NEW QUESTION 33
A common estimation unit for Agile projects is:

  • A. Use-case points.
  • B. Lines of code.
  • C. Function points
  • D. Story points.

Answer: D

 

NEW QUESTION 34
A high-performance Agile team:

  • A. is fully committed to team success yet respects the prescribed roles and titles of team members.
  • B. produces a high volume of business value through intensive collaboration and avoidance of conflict.
  • C. is self-organizing, empowered to make decisions, and consensus-driven, with constructive disagreement.
  • D. owns its decisions and commitments and is motivated to succeed at any cost.

Answer: C

 

NEW QUESTION 35
Who is responsible for making sure that each user story is associated with at least one user role or persona?

  • A. Customer
  • B. Developer
  • C. Persona
  • D. User

Answer: A

 

NEW QUESTION 36
What are three processes used to begin an Agile project?

  • A. Visioning, Product Roadmap Planning, and Product Backlog Definition
  • B. Visioning, Product Backlog Definition, and Project Charter Creation
  • C. Burndown chart, Product Roadmap, and sprints'length
  • D. Iterations, Product Road map Planning, and Number of Sprint Iterations

Answer: A

 

NEW QUESTION 37
In the Lean process, the focus is on:

  • A. Managing team efficiency.
  • B. Using the optimal resources.
  • C. Optimizing completed work across the process stream.
  • D. Cross training the team to eliminate bottlenecks.

Answer: C

 

NEW QUESTION 38
In reference to Scrum, each sprint should produce:

  • A. An increment of potentially testable product functionality.
  • B. Arelease with testable and measurable functionality.
  • C. An increment of potentially shippable product functionality.
  • D. Aset of documented product requirements and specifications.

Answer: C

 

NEW QUESTION 39
When are acceptance tests typically written for a user story?

  • A. At the start of Product Backlog prioritization planning
  • B. After writing the story, but before coding begins
  • C. After estimating the Product Backlog, but before Sprint planning begins
  • D. After coding the story, but before user acceptance testing begins

Answer: A

 

NEW QUESTION 40
According to the fundamental principles of Lean Management, errors result from:

  • A. Insufficient management oversight of projects and operations.
  • B. Inadequate user requirements and documentation.
  • C. Misjudgment made by project teams and operations staff.
  • D. Flaws in development and production systems.

Answer: D

 