TopicDetails
Topic 1
  • Understand the agile ways of working, key terms and techniques
Topic 2
  • Understand how PRINCE2 principles, themes, processes and management products are tailored and/or applied in an agile context
Topic 3
  • Understand the focus areas in an agile contex
  • Understand key concepts relating to PRINCE2
Topic 4
  • Understand key concepts relating to projects and PRINCE2 Agile

 

NEW QUESTION 18
Why are team working agreement produced?

  • A. To evolve the effectiveness and behaviors of the self-organizing team by agreeing values
  • B. To ensure that the delivery team members comply with company policy
  • C. To create structure so that the team manager can assess individual performance
  • D. To make the team rules visible to the project manager for monitoring purposes

Answer: A

Explanation:
Reference https://publications.axelos.com/prince2agile2016/content.aspx?page=pra_126&showNav=true&expandNav=true

 

NEW QUESTION 19
Which is a key objective of running a workshop?

  • A. To communicate decisions to the wider stakeholder community
  • B. To make daily progress visible to the delivery team and key stakeholders
  • C. To make day-to-day decisions on behalf of the delivery team within a sprint
  • D. To encourage collaboration and create the defined outputs from the event

Answer: D

 

NEW QUESTION 20
Which is a reason for releasing a product into a staging area?

  • A. It enables the faster delivery of changes
  • B. It enables a phased Waterfall approach
  • C. It supports management by exception
  • D. It supports regulatory compliance checking

Answer: D

Explanation:
Reference:
%20and%20verification%20process

 

NEW QUESTION 21
Which statement about velocity is CORRECT?

  • A. It is shown by the ideal line on a bum-down chart
  • B. It describes how much work is getting done
  • C. It tracks the time and cost of a timebox
  • D. It is based on the concept of rationalism

Answer: B

 

NEW QUESTION 22
Which statement explains the target 'be on time and hit deadlines' for flexible delivery?

  • A. It enables team dynamics to remain the same
  • B. It sets the project baseline at the correct level
  • C. It reduces testing in order to meet deadlines
  • D. It improves the supplier's reputation with the customer

Answer: C

 

NEW QUESTION 23
How is the 'tailor to suit the project' principle applied in an agile context?

  • A. By emphasizing tolerances on what is being delivered
  • B. By flexing what is produced to stay in control and deliver value
  • C. By fitting releases into planned management stages
  • D. By using the Agilometer to assess the project environment

Answer: B

 

NEW QUESTION 24
Which statement about the 'protect the level of quality' target is CORRECT?

  • A. It delivers the early realization of benefits
  • B. It gives confidence on the progress of the project
  • C. It is achieved by using the same team members
  • D. It is achieved by allowing enough time for testing

Answer: A

Explanation:
Reference:
%20level%20is%20met

 

NEW QUESTION 25
Which statement explains the PRINCE2 Agile behavior of 'exploration'?

  • A. It displays the progress rate to everyone using burn-down charts
  • B. It seeks out feedback collaboratively from project stakeholders
  • C. It empowers the project management team at the delivery level
  • D. It uses the most effective channel to communicate information

Answer: B

 

NEW QUESTION 26
Which BEST describes the senior user role when tailoring the organization theme?

  • A. An 'agile sponsor'
  • B. A 'coach'
  • C. An 'executive sponsor'
  • D. A 'super product owner'

Answer: D

 

NEW QUESTION 27
What should the business case state about the minimum viable product (MVP)?

  • A. What the MVP is
  • B. When the MVP will be defined
  • C. That the MVP is the same as project viability
  • D. That the MVP must go into operational use

Answer: D

 

NEW QUESTION 28
Which is NOT one of the core concepts of Lean Startup that apply to PRINCE2?

  • A. To fail fast, if you are going to fail
  • B. To build, measure, learn from your experiences
  • C. To create a minimum viable product to manage uncertainty
  • D. To use empiricism, based on knowledge that comes from experience

Answer: D

 

NEW QUESTION 29
How does agile address the risk associated with the project not being fully understood at the beginning?

  • A. By avoiding too much detail at the start
  • B. By allowing a lot of detail at the start
  • C. By requiring details at the start
  • D. By preventing the analysis of details at the start

Answer: D

 

NEW QUESTION 30
Which statement explains the setting of the cost tolerance for a project in an agile context?

  • A. Cost tolerance can be fixed and flexed
  • B. Cost tolerance is fixed
  • C. Cost tolerance can be fixed or flexed
  • D. Cost tolerance is flexed

Answer: D

 

NEW QUESTION 31
Which two statements are key responsibilities of supplier representative?
1. They highlight areas that the project may impact from a technical perspective.
2. They are partially assigned to the delivery team.
3. They create the project's specialist products.
4. They prioritize requirements.

  • A. 3 and 4
  • B. 1 and 2
  • C. 1 and 4
  • D. 2 and 3

Answer: C

 

NEW QUESTION 32
Which statement about the 'directing a project' process is CORRECT?

  • A. The project board should attend regular project progress meetings
  • B. The project board should make decisions based on the Agilometer risks
  • C. A project board member should fulfill the product owner role within a delivery team
  • D. The project board should increase the stage-level time tolerance

Answer: C

 

NEW QUESTION 33
Which is a benefit of the Lean Startup approach to releasing a product?

  • A. It enables the release plans to be synchronized with the PRINCE2 plans
  • B. It provide a technique to reduce the testing of a product before release
  • C. It reduces the number of people needed to manage a release of a product
  • D. It provides quick feedback that can be responded to at the earliest opportunity

Answer: A

 

NEW QUESTION 34
In Scrum, what answers the question 'what can be done this sprint?'

  • A. Sprint review
  • B. Daily scrum
  • C. Increment
  • D. Sprint planning

Answer: B

 

NEW QUESTION 35
Which process can take place during a release review workshop?

  • A. Controlling a stage
  • B. Directing a project
  • C. Managing product delivery
  • D. Managing a stage boundary

Answer: C

 