NEW QUESTION 18
Why are team working agreement produced?
- A. To evolve the effectiveness and behaviors of the self-organizing team by agreeing values
- B. To ensure that the delivery team members comply with company policy
- C. To create structure so that the team manager can assess individual performance
- D. To make the team rules visible to the project manager for monitoring purposes
Answer: A
Explanation:
Reference https://publications.axelos.com/prince2agile2016/content.aspx?page=pra_126&showNav=true&expandNav=true
NEW QUESTION 19
Which is a key objective of running a workshop?
- A. To communicate decisions to the wider stakeholder community
- B. To make daily progress visible to the delivery team and key stakeholders
- C. To make day-to-day decisions on behalf of the delivery team within a sprint
- D. To encourage collaboration and create the defined outputs from the event
Answer: D
NEW QUESTION 20
Which is a reason for releasing a product into a staging area?
- A. It enables the faster delivery of changes
- B. It enables a phased Waterfall approach
- C. It supports management by exception
- D. It supports regulatory compliance checking
Answer: D
Explanation:
Reference:
%20and%20verification%20process
NEW QUESTION 21
Which statement about velocity is CORRECT?
- A. It is shown by the ideal line on a bum-down chart
- B. It describes how much work is getting done
- C. It tracks the time and cost of a timebox
- D. It is based on the concept of rationalism
Answer: B
NEW QUESTION 22
Which statement explains the target 'be on time and hit deadlines' for flexible delivery?
- A. It enables team dynamics to remain the same
- B. It sets the project baseline at the correct level
- C. It reduces testing in order to meet deadlines
- D. It improves the supplier's reputation with the customer
Answer: C
NEW QUESTION 23
How is the 'tailor to suit the project' principle applied in an agile context?
- A. By emphasizing tolerances on what is being delivered
- B. By flexing what is produced to stay in control and deliver value
- C. By fitting releases into planned management stages
- D. By using the Agilometer to assess the project environment
Answer: B
NEW QUESTION 24
Which statement about the 'protect the level of quality' target is CORRECT?
- A. It delivers the early realization of benefits
- B. It gives confidence on the progress of the project
- C. It is achieved by using the same team members
- D. It is achieved by allowing enough time for testing
Answer: A
Explanation:
Reference:
%20level%20is%20met
NEW QUESTION 25
Which statement explains the PRINCE2 Agile behavior of 'exploration'?
- A. It displays the progress rate to everyone using burn-down charts
- B. It seeks out feedback collaboratively from project stakeholders
- C. It empowers the project management team at the delivery level
- D. It uses the most effective channel to communicate information
Answer: B
NEW QUESTION 26
Which BEST describes the senior user role when tailoring the organization theme?
- A. An 'agile sponsor'
- B. A 'coach'
- C. An 'executive sponsor'
- D. A 'super product owner'
Answer: D
NEW QUESTION 27
What should the business case state about the minimum viable product (MVP)?
- A. What the MVP is
- B. When the MVP will be defined
- C. That the MVP is the same as project viability
- D. That the MVP must go into operational use
Answer: D
NEW QUESTION 28
Which is NOT one of the core concepts of Lean Startup that apply to PRINCE2?
- A. To fail fast, if you are going to fail
- B. To build, measure, learn from your experiences
- C. To create a minimum viable product to manage uncertainty
- D. To use empiricism, based on knowledge that comes from experience
Answer: D
NEW QUESTION 29
How does agile address the risk associated with the project not being fully understood at the beginning?
- A. By avoiding too much detail at the start
- B. By allowing a lot of detail at the start
- C. By requiring details at the start
- D. By preventing the analysis of details at the start
Answer: D
NEW QUESTION 30
Which statement explains the setting of the cost tolerance for a project in an agile context?
- A. Cost tolerance can be fixed and flexed
- B. Cost tolerance is fixed
- C. Cost tolerance can be fixed or flexed
- D. Cost tolerance is flexed
Answer: D
NEW QUESTION 31
Which two statements are key responsibilities of supplier representative?
1. They highlight areas that the project may impact from a technical perspective.
2. They are partially assigned to the delivery team.
3. They create the project's specialist products.
4. They prioritize requirements.
- A. 3 and 4
- B. 1 and 2
- C. 1 and 4
- D. 2 and 3
Answer: C
NEW QUESTION 32
Which statement about the 'directing a project' process is CORRECT?
- A. The project board should attend regular project progress meetings
- B. The project board should make decisions based on the Agilometer risks
- C. A project board member should fulfill the product owner role within a delivery team
- D. The project board should increase the stage-level time tolerance
Answer: C
NEW QUESTION 33
Which is a benefit of the Lean Startup approach to releasing a product?
- A. It enables the release plans to be synchronized with the PRINCE2 plans
- B. It provide a technique to reduce the testing of a product before release
- C. It reduces the number of people needed to manage a release of a product
- D. It provides quick feedback that can be responded to at the earliest opportunity
Answer: A
NEW QUESTION 34
In Scrum, what answers the question 'what can be done this sprint?'
- A. Sprint review
- B. Daily scrum
- C. Increment
- D. Sprint planning
Answer: B
NEW QUESTION 35
Which process can take place during a release review workshop?
- A. Controlling a stage
- B. Directing a project
- C. Managing product delivery
- D. Managing a stage boundary
Answer: C