NEW QUESTION 21
A customer project must be finished at a given due date. The project consists of WBS elements and networks. What scheduling type do you use?

  • A. Forward
  • B. Current date
  • C. Only capacity requirements
  • D. Backward

Answer: D

 

NEW QUESTION 22
You are using WBS elements and activities are NOT assigned. Which statements apply to the maintenance of the actual start and finish? Note: There are 2 correct Answers to this question.

  • A. You can always maintain the actual start and finish date of a WBS element.
  • B. You can always maintain the actual start if the WBS element has the status "Released" or "Partially released".
  • C. You can only maintain the actual start of a WBS element if the finish date is not maintained.
  • D. You can only maintain the actual finish if all lower-level WBS elements have an actual finish date and the status of the WBS element is "Released".

Answer: B,D

 

NEW QUESTION 23
A service company uses project management and they complain that the system does not prevent their project managers from exceeding their budgets. What actions do you have to take to solve the problem?

  • A. Activate availability control for the WBS elements. Define the tolerance limits on each WBS element.
  • B. Activate commitment management in the project definition. Enter the budget in the master data of the top WBS element.
  • C. Activate availability control in the assigned budget profile. Define the tolerance limits in customizing.
  • D. Activate availability control for projects in the controlling area. Enter the plan data for each WBS element.

Answer: C

 

NEW QUESTION 24
Which report can use user-specific layouts?

  • A. Hierarchical report
  • B. Enhanced individual overview
  • C. Cost element report
  • D. Line item report

Answer: D

 

NEW QUESTION 25
Which of the following data can be maintained in a standard network? Note: There are 3 correct Answers to this question.

  • A. Document information records
  • B. Basic dates for activities
  • C. Material components
  • D. Relationships
  • E. Internally processed activities

Answer: C,D,E

 

NEW QUESTION 26
You used reductions to reduce the scheduled duration of all internally-processed activities in your project. However, the duration did not changed after overall network scheduling.
What do you check? Note: There are 2 correct Answers to this question.

  • A. If the appropriate reduction type is set in the parameters for network scheduling
  • B. If the reduction strategy is set in the network header
  • C. If the maximum reduction level is less than 100
  • D. If the reduction strategy is set in each activity

Answer: A,B

 

NEW QUESTION 27
You want to use billing for a customer project. Which customizing object controls the billing of sales order items?

  • A. Requirements type
  • B. Requirements class
  • C. Schedule line category
  • D. Item category

Answer: D

 

NEW QUESTION 28
You want to use subnetworks during the project. Which of the following statements describes subnetworks?

  • A. A subnetwork cannot be defined for a superior subnetwork.
  • B. Maintenance orders can be defined as subnetworks.
  • C. Subnetworks must be scheduled separately from the superior network.
  • D. The scheduling type of a subnetwork is always copied from the superior network.

Answer: B

 

NEW QUESTION 29
You want to set up the field selection of the Cross-Application Time Sheet (CATS) in Customizing. Which influencing field do you use?

  • A. Data entry profile
  • B. Network profile
  • C. Network type
  • D. Project profile

Answer: A

 

NEW QUESTION 30
Where do you control whether a project stock is managed as valuated or non-valuated project stock?

  • A. In the project definition
  • B. In the network activity
  • C. In the WBS element
  • D. In the material master

Answer: A

 

NEW QUESTION 31
Which objects do you have to maintain to enable automatic assignment of material components to the project? Note: There are 2 correct Answers to this question.

  • A. Network activity
  • B. BOM item
  • C. Material master
  • D. WBS element

Answer: A,B

 

NEW QUESTION 32
How can you record external service activities with service master data? Note: There are 2 correct Answers to this question.

  • A. Confirm the network activity for external services.
  • B. Confirm the activities in the Cross-Application Time Sheet (CATS).
  • C. Post a goods receipt in the goods movement application (MIGO).
  • D. Create a service entry sheet.

Answer: B,D

 

NEW QUESTION 33
The system status of a WBS element is created (CRTD). Which business process is allowed for this WBS element?

  • A. Activity allocation
  • B. Calculation of actual values
  • C. Creation of purchase orders
  • D. Goods receipt for purchase orders

Answer: C

 

NEW QUESTION 34
Where do you maintain the length of the project ID?

  • A. Project coding mask
  • B. Project profile
  • C. Project type
  • D. Special characters

Answer: A

 

NEW QUESTION 35
You are using networks and external activities in your project. The purchase requisition has been created. What is the sequence for the following business transactions and documents?

  • A. Vendor selection -> Purchase order handling -> Purchase order monitoring -> Goods receipt
  • B. Credit limit check -> Acceptance of performed services -> Vendor selection -> Purchase order handling
    -> Purchase order monitoring -> Goods receipt -> Invoice receipt
  • C. Vendor selection -> Purchase order handling -> Invoice receipt -> Purchase order monitoring -> Goods receipt
  • D. Vendor selection -> Purchase order creation -> Service entry sheet creation -> Service entry sheet approval

Answer: D

 

NEW QUESTION 36
You want to make sure that certain tasks must start on a given date. Where can you maintain constraints for start dates?

  • A. Milestone
  • B. Network header
  • C. Activity
  • D. Activity element

Answer: C

 

NEW QUESTION 37
Which sales documents can update planned revenues on WBS elements? Note: There are 2 correct Answers to this question.

  • A. Sales order
  • B. Inquiry
  • C. Billing
  • D. Quotation

Answer: A,D

 

NEW QUESTION 38
In your logistics project, you want to carry out the internal project work as soon as possible. What do you have to maintain in capacity requirements planning?

  • A. Control key of an activity
  • B. Capacity planner group in the network header
  • C. Scheduling and distribution key
  • D. Scheduling and capacity category

Answer: A

 

NEW QUESTION 39
How can you confirm the working hours of different work centers for a single activity?

  • A. Assign multiple work centers to the activity.
  • B. Enter direct activity allocation assigning multiple work centers.
  • C. Create multiple confirmations for the activity and use the appropriate work center for each confirmation.
  • D. Enter multiple work centers within a single confirmation.

Answer: B

 

NEW QUESTION 40
What functionality can you perform with activity elements?

  • A. Assign material
  • B. Assign work centers and capacities
  • C. Schedule WBS elements
  • D. Create relationships

Answer: D

 

NEW QUESTION 41
What are valid procurement types for stock items? Note: There are 3 correct Answers to this question.

  • A. Third-party order
  • B. Purchase requisition and Reservation for WBS element
  • C. Preliminary purchase requisition for WBS element
  • D. Planned order
  • E. Reservation for WBS element

Answer: B,C,E

 

NEW QUESTION 42
Which organizational structures are required for network activities? Note: There are 3 correct Answers to this question.

  • A. Plant
  • B. Sales organization
  • C. Controlling area
  • D. Operating concern
  • E. Company code

Answer: A,C,E

 

NEW QUESTION 43
Where can you define a network as "header-account-assigned" or "activity-account-assigned"?

  • A. Parameters for the network type
  • B. Network profile
  • C. Network type
  • D. Project profile

Answer: A

 