NEW QUESTION 88
Which of the following tools are used for rapid database migration?
There are 2 correct answers to this question.
Response:

  • A. Software Update Manager (SUM)
  • B. Database Migration Option (DMO)
  • C. SAP Solution Manager
  • D. SWPM (software provisioning manager)

Answer: A,B

 

NEW QUESTION 89
Which of the following are levels in the structure of an SAP Best practices solution package? There are 2 correct answers to this question.

  • A. Configuration guides
  • B. Building blocks
  • C. Scope items
  • D. Business process scenarios

Answer: B,C

 

NEW QUESTION 90
In which phase you execute the User Acceptance Test?
Please choose the correct answer.
Response:

  • A. Final Preparation
  • B. Build and Test
  • C. Deploy
  • D. Realize

Answer: D

 

NEW QUESTION 91
What is the most granular level of the methodology you can view in the Roadmap Viewer?
Please choose the correct answer.
Response:

  • A. Deliverables
  • B. Task
  • C. Scenario
  • D. Phase

Answer: B

 

NEW QUESTION 92
What is the objective of a sprint retrospective meeting?
Please choose the correct answer.
Response:

  • A. Provide formal feedback to the project manager
  • B. Define the stakeholder management approach
  • C. Improve the SCRUM process
  • D. Review andprioritize the backlog

Answer: C

 

NEW QUESTION 93
In which SAP Activate methodology phase does the team complete the Transformation Strategy? Please choose the correct answer.

  • A. Explore
  • B. Deploy
  • C. Prepare
  • D. Realize

Answer: C

 

NEW QUESTION 94
Which of the following are part of the 10 SAP Quality Principles?
There are 2 correct answers to this question.
Response:

  • A. Achieve production readiness.
  • B. Start scoping early.
  • C. Use standard functionality optionally.
  • D. Plan one phase at a time.

Answer: A,B

 

NEW QUESTION 95
What are some responsibilities of customer key users after go-live of an SAP S/4HANA Cloud project?

  • A. Complete the implementation activities as assigned.
  • B. Monitor internal/external communications such as printers and integration with third-parties.
  • C. Search for solutions and process incidents from end users directly andwhen necessary, request help from SAP.
  • D. Responsible for inspection and approval of results and of the overall project.
  • E. Manage Users and Task Assignment.

Answer: B,C,E

 

NEW QUESTION 96
Why do you use the Implementation Portal for SAP S/4HANA Cloud?

  • A. To use the guided workflow to integrate SAP Cloud solutions.
  • B. To monitor the progress of implementation tasks in real time.
  • C. To use asan input for Fit-to-Standard workshops that helps the team understand areas to spend more time on during workshops.
  • D. To manage implementation tasks based on SAP Activate Methodology that are automatically generated and adapted to thecustomer's scope.

Answer: B,D

 

NEW QUESTION 97
Which of the following are available in the initial SAP Methodologies JAM Page?
There are 2 correct answers to this question.
Response:

  • A. Summary
  • B. Task description
  • C. Roadmaps
  • D. Accelerators

Answer: C,D

 

NEW QUESTION 98
Which estimation technique canbe used in Agile project delivery to size the user stories during sprint planning?
Please choose the correct answer.
Response:

  • A. Detailed bottom-up effort estimate by the SCRUM Master in story points based on the user story complexity
  • B. Relative estimate in ideal person days that reflects the best estimate provided by the project team
  • C. Product Owner's relative estimate of the effort that will be needed toimplement the user story
  • D. Detailed bottom-up effort estimate the breaks each user story up into hours or shorter tasks

Answer: B

 

NEW QUESTION 99
Which artifacts in the testing workstream are created within the realize phase for the "new implementation of SAP S/4HANA Cloud" transition path? There are 2 correct answers to this question.

  • A. Reporting functional specifications
  • B. Functional specifications
  • C. Functional test scenarios
  • D. User acceptance test-plan

Answer: C,D

 

NEW QUESTION 100
What is the purpose of thescrumboard?
Please choose the correct answer.
Response:

  • A. To manage the resource load
  • B. To document the results of integration testing
  • C. To show the functional breakdown of the solution scope
  • D. To visualize team progress

Answer: D

 

NEW QUESTION 101
Identify the two landscape transformation specific tasks in the explore phase. There are 2 correct answers to this question.

  • A. Setup Landscape Transformation Software
  • B. Perform Client transfer
  • C. Define the Data Migration Architecture
  • D. Run a landscape transformation assessment

Answer: A,D

 

NEW QUESTION 102
What are the responsibilities of the Project Team on level 4 in the picture below?

There are 2 correct answers to this question.
Response:

  • A. Set business priorities, goals and objectives
  • B. Set Project policy, standards and oversight
  • C. Identify and resolve issues and risks
  • D. Perform status reporting and communication

Answer: C,D

 

NEW QUESTION 103
In which phase do you create a prioritized list of user requirements?
Please choose the correct answer.
Response:

  • A. Explore
  • B. Deploy
  • C. Prepare
  • D. Realize

Answer: A

 

NEW QUESTION 104
......

Accurate & Verified Answers As Seen in the Real Exam here: https://www.prepawaypdf.com/SAP/C_ACTIVATE12-practice-exam-dumps.html