NEW QUESTION 122
The project is approaching the end of stage 3, and stage 4 is being planned as part of the 'managing a stage boundary' process.
Which action should the project manager carry out as part of the 'update the project plan' activity?
- A. Include the tolerances for the work package 'delivered pilot courses' in the project plan.
- B. Ensure that the team manager for the work package 'delivered pilot courses' is included as a resource.
- C. Include the actual time and cost of the work to prepare the 'marketing materials' in the project plan.
- D. Update the project's business case to show any new key risks that have been identified.
Answer: C
Explanation:
Explanation/Reference: https://www.prince2primer.com/prince2-2017-update-project-plan-business-case/
NEW QUESTION 123
Who sets the tolerances for a work package?
- A. The project board
- B. Corporate or programme management
- C. The team manager
- D. The project manager
Answer: D
Explanation:
Explanation/Reference:
Risk Theme
Testlet 1
Additional Information
A photographer from Portraits Ltd, a professional photographic company, has taken on the role of Team Manager after taking some time to understand the requirements of the project. A contract for their services has been set up and is being monitored by the Purchasing Manager and a Work Package has been agreed. This contract specifies that the photographer must arrange a meeting with the Engineering Manager to establish a schedule for the photo sessions to minimize the impact on the Engineering staff. This meeting should have occurred by now.
The Engineering Manager was made aware of this requirement but when asked he reported that he has received no communication from the photographer. The Project Manager has tried to call the photographer and has had no response. The Project Manager believes there is a risk that Portraits Ltd are overbooking work and prioritizing other clients' work. If Portraits ltd do not deliver on schedule the project will be delayed and the expected benefits will be reduced.
The contract is to be reviewed and Portraits Ltd reminded of their agreement.
NEW QUESTION 124
The development of the 'e-learning course' will be outsourced to an external supplier and their key members will join the project management team. The supplier wants to keep their work processes confidential and not share these with ABC Company. ABC Company has agreed.
Who should approve the external supplier's team plan?
- A. Supplier assurance
- B. Senior supplier
- C. Corporate, programme management or customer
- D. Project manager
Answer: C
Explanation:
Explanation
NEW QUESTION 125
Which of the following statements is FALSE regarding the Continued Business Justification?
- A. The justification for the project should remain vabd.
- B. The justification for the project may change.
- C. The justification for the project must remain the same throughout the project.
- D. If the project is no longer justified it should be stopped.
Answer: A
NEW QUESTION 126
Project Scenario
Calendar Project (Note: The companies and people within the scenario are fictional.)
There has been a reduction in fie number of orders at the MNO Manufacturing Company due in part to the increased marketing activities of its competitors. To help counter this, the company has decided to create a promotional calendar for next year for all its current and prospective customers. The end product of this project will be a prepared calendar pack, ready for printing. The design of the calendar will be similar to one sent out previously, and must reflect the company image as described in the existing corporate branding standards. Another project is currently producing a new company logo when is to be printed on each page of the promotional calendar. The prepared calendar pack will consist of:
Design for each month - correctly showing at public holidays and new company logo Selected photographs- 12 professionally-produced photographs, showing different members of staff
--
--
Selected paper and selected envelope - for printing and mailing the calendar Chosen label design - a competition to design a label will be held as part of this project List of customers - names and addresses of customers to whom the calendar will be sent.
-
The project is currently in initiation and will have two further stages:
Stage 2 will include tie activities to: Create the customer fast using information from the Accounts and Marketing departments
-
---- --
Confirm compliance with the Data Protection Legislation Create a design for each month - this will be done by the internal creative team Select and appoint a professional photographer Gather photograph design ideas from previous project and agree photographic session schedule Prepare a production cost forecast Select paper and envelope.
Stage 3 will include the activities to:
---
Produce and select tie professionally-taken photographs Hold the label design competition and choose the label design Assemble the prepared calendar pack.
A production cost forecast, based on the options and costs for the paper, envelope, printing and marketing of the calendar is to be produced in stage 2. However, the actual production and distribution of the calendars is not within the scope of the project. The product cost forecast will be reviewed by the Project Board to determine whether tie project should continue.
It is now 05 October and the prepared calendar pack must be delivered to the print company by 30 November, to enable printing and distribution of the calendar in time for Christmas. The cost of the activities to develop the specialist products and the cost of the project management activities are estimated to be (GBP)20,000. There is a project time tolerance of +1 week /-2 weeks and a project cost tolerance of +(GBP)6,000 / -(GBP)6,000. A change budget of (GBP)500 has been allocated but there is no risk budget.
At the end of initiation there is +1 week 1-2 weeks time tolerance for this project. Which statement is true?
- A. All of the project level time tolerance can be allocated to stage 2.
- B. The Stage Plan for stage 2 could create some additional project time tolerance by allowing no time tolerance in Team Plans.
- C. Additional time tolerance for the project could be found by adding extra resources without affecting other tolerances.
- D. There can be no time tolerances for any of the stages.
Answer: A
NEW QUESTION 127
Scenario
Additional Information
Further information on some resources who could be involved in the project:
Outcome Account Manager: He represents Outcome which is a recruitment agency that provides specialist outsourcing resources. Outcome provided the consultants who carried out the feasibility study and the same consultants will be providing support and guidance to the Information Technology and Facilities teams during the project.
Director of Finance Division: She was transferred from the Information Technology Division 12 months ago. She is responsible for ensuring a cost-conscious approach is adopted in all operational and project activities across the Ministry of Food Hygiene.
Hardware Manager: Reports to the Director of Information Technology. He provides computer hardware to all business functions but has little awareness of the needs of his colleagues working in software.
Payroll Manager: Reports to the Director of Finance. He is a very experienced and efficient qualified accountant who has much of the responsibility of running the Finance Division on behalf of the Director of Finance. He has been involved in drafting the Ministry's business strategy and assisting in a full business risk assessment. He also drafted the corporate Business Case standards.
Which 2 alternative actions apply to the proposed Senior Supplier for this project?
- A. Add 'Director of Facilities' because he is responsible for the design of the future organization, processes, systems and operation models for Facilities.
- B. Add 'Hardware Manager' because he provides computer hardware to all business functions and will be impacted by the outcome.
- C. Replace with 'Director of Facilities' because he supports the initiative and has many ideas about how to improve the service.
- D. Remove because she only represents the Information Technology Division.
- E. Retain because she is responsible for the design of the future Information Technology organization and working practices.
Answer: A,E
NEW QUESTION 128
During the 'create the project plan' activity as part of the initiation stage, the project manager identifies several threats to the project timescales. These threats relate to stage 3 products. Therefore, the project manager decides to wait until the end of stage 2 to assess the risks to the project plan.
Is this an appropriate application of the plans theme, and why?
- A. No, because the risks inherent in the project plan should be assessed, and the plan modified to manage them.
- B. No, because the risk actions to manage project-level threats should be recorded in the risk register.
- C. Yes, because risk planning should take place in the stage plan before the risks occur, not in the project plan.
- D. Yes, because detailed planning of stage 3 should take place after completion of the stage 2 products.
Answer: A
Explanation:
Explanation
Reference
https://books.google.com.pk/books?id=CSm7x74Px94C&pg=PA181&lpg=PA181&dq=prince2+risks+inherent+
NEW QUESTION 129
What products will be impacted by this change?
- A. All of the project's products which relate to or include services provided by the Facilities Division.
- B. All of the project's products created so far.
- C. No products would need to be changed but some will need to be removed from the project.
- D. Only those products created in the first three weeks of stage 3.
Answer: C
NEW QUESTION 130
Using the Project Scenario and the Extract from Stage Plan for stage 3 provided as additional intonation for this question in the Scenario Booklet, answer the following 5 questions.
The Stage Plan for stage 3 has been produced.
The Engineering Manager insists that there are to be no interruptions to operations whilst photographs are being taken of the engineering staff performing their everyday duties and operating machinery. Two weeks ago the professional photographer produced the photo session schedule based on the operational staff schedule. The operational staff schedule is produced weekly and maintained by the Engineering Manager.
None of the £500 change budget has been used to date and this is available for the stage.
Which 2 statements apply to the External dependencies section?
- A. Move entry 5 to Plan description because the new company logo will be delivered during stage 3.
- B. Delete entry 7 because it should be shown in the Product Description for the label design.
- C. Delete entry 5 because the new company logo is being delivered by a separate project and will be detailed in the plans for that project.
- D. Move entry 5 to Plan prerequisites because the new company logo will influence the label designs.
- E. Delete entry 6 because the customer details were used in stage 2 to create the customer list.
Answer: B,E
NEW QUESTION 131
A change authority has been appointed for the project. During the development of the 'classroom-based training material', a large number of changes were proposed to the design of the 'e-learning course'. Therefore, the change authority has decided to use the Moscow technique to prioritize changes based on the impact they will have on completing each stage on time.
Is this an appropriate application of the Moscow technique, and why?
- A. No, because it should be used to prioritize change based on the project's business justification.
- B. Yes, because it should be used to prioritize change based on the estimated impact on time.
- C. Yes, because it is a prioritization technique that should be used to prioritize a product's quality criteria.
- D. No, because it should define scope tolerances, supporting the management by exception principle.
Answer: B
Explanation:
Explanation/Reference: https://en.wikipedia.org/wiki/MoSCoW_method
NEW QUESTION 132
As the project approaches the end of stage 2, the Project Manager has requested a Product Status Account to ensure that all products are at their expected point of development. Although the list of customers has been quality reviewed, it has not been baselined because the Marketing department have not provided all of the prospective customers' details. What initial action should the Project Manager take?
- A. Check the target sign-off date for the list of customers.
- B. Update the product status to baselined and obtain a commitment from the Marketing department to finish this work within the next few days.
- C. Delay producing the End Stage Report until the list of customers has been baselined.
- D. Raise an Exception Report to the Project Board to highlight the issue.
Answer: A
NEW QUESTION 133
The Health and Safety Training Project is closing as planned. According to the contract terms, suppliers must submit all invoices within one week of project closure. The project manager will issue a project closure notification informing all suppliers of this invoicing deadline as part of the 'recommended project closure' activity.
Is this appropriate, and why?
- A. No, because the project manager should notify stakeholders using the approved project closure notification.
- B. Yes, because a project closure notification should be sent to suppliers as part of the 'closing project' process.
- C. No, because the project board should issue a project closure notification as part of the 'directing a project' process.
- D. Yes, because the project board should approve the project closure notification drafted by the project manager.
Answer: B
NEW QUESTION 134
Project Scenario - Health and Safety Training Project:
ABC Company is a well-established training company that uses a standard model to develop training materials and deliver courses to customers.
ABC Company has commissioned a project in response to recent changes in government legislation relating to health and safety on construction sites. The project will deliver "capability to provide health and safety training", including the materials needed for classroom-based training and e-learning. The expected benefits for construction companies include a reduction in lost days and legal costs due to accidents.
The e-learning course will be developed by a specialist external consultancy. The materials for classroom-based training will be delivered by ABC Company's development team. All course materials will be piloted before they are used. ABC Company will deliver training to its customers and also hopes to sell the course materials to other training companies as part of their operational business. ABC Company will use their own sales and marketing departments to promote the courses.
The legislation requires construction companies to comply with the new legislation within two years. The course materials and trainers have to be accredited by a government agency before courses can be delivered.
ABC Company is planning to deliver pilot courses within five months of starting the project.
The ABC Company standard development model for new courses recommends the following stages:
End of the Project scenario.
Additional Information:
The Chief Executive Officer (CEO) founded the company five years ago. Under her leadership, ABC Company has grown quickly into a successful training company. It delivers a range of accredited professional training.
The Finance Director is also a founder member of ABC Company and is responsible for authorizing budgets for the Operations and Development Teams. She authorizes all large contracts personally.
The Purchasing Manager reports to the Finance Director and is responsible for managing and monitoring supplier contracts.
The Operations Director is responsible for the delivery off all training and for the training development budget. His department organizes courses, venues and trainers. They work with the Product and the Sales teams to provide a comprehensive training schedule. ABC Company's IT manager reports to the Operations Director.
The Business Development Director has recently been appointed to identify new training needs and propose new products. She will work with the Operations. Director to ensure a cost-conscious approach and that appropriate development technologies are used for the health and safety course.
The Training Development Manager reports to the Business Development Director and is responsible for developing training materials and gaining accreditation, in accordance with the standard course development model. Course developers in his team have skills in a range of development technologies and are allocated to projects as needed.
The Training Delivery Manager, who reports to the Operations Director, is responsible for ensuring that internal and external trainers deliver ABC Company training courses to the required standard. He also checks course materials to ensure they are fit for purpose and of the required quality.
The Central Services Director has responsibility for corporate communications, facilities management and configuration management. He recently led a project to consolidate all company quality systems into one quality management system and set up a corporate quality department, now managed by the Corporate Quality Manager.
The Corporate Document Manager reports to the Central Services Director. She helped establish the company's document management system and now operates it across the business. She manages a team of administrators and contracts staff when workload is high.
The Sales Director joined ABC Company two months ago and is keen to establish himself by suggesting new markets for the courses and material. All account managers and the marketing team report to him. They promote existing training courses to other training companies and existing customers.
End of the additional information.
CHANGE
A request has been received from a user to add the function to pay by credit card to the 'amended course booking procedures' for the 'e-learning course'. The user has suggested that sales of the course will be reduced if this change is not implemented.
Here are three actions relating to this request for change.
Which role (A-E) should carry out each action?
Choose only one role for each action. Each role can be used once, more than once, or not at all.
Answer:
Explanation:
Explanation
NEW QUESTION 135
Using the Project Scenario and the Extract from Stage Plan for stage 3 provided as additional intonation for this question in the Scenario Booklet, answer the following 5 questions.
The Stage Plan for stage 3 has been produced.
The Engineering Manager insists that there are to be no interruptions to operations whilst photographs are being taken of the engineering staff performing their everyday duties and operating machinery. Two weeks ago the professional photographer produced the photo session schedule based on the operational staff schedule. The operational staff schedule is produced weekly and maintained by the Engineering Manager.
None of the £500 change budget has been used to date and this is available for the stage.
Which 2 statements apply to the Plan prerequisites section?
- A. Delete entry 3 because the production cost forecast is a deliverable of stage 2, not a prerequisite for stage 3.
- B. Delete entry 2 because these are project benefits not prerequisites of the stage.
- C. Add 'Compliance with the Data Protection Act'.
- D. Delete entry 4 because the customer list is a deliverable of stage 2, not a prerequisite for stage 3.
- E. Add 'Engineering team must be made available for photos'.
Answer: B,D
NEW QUESTION 136
Which of the following activities is the Executive responsible for?
- A. Ensure the desired outcome of the project is specified
- B. Responsible for the benefits review plan
- C. Responsible for the Benefits Review Plan post project
- D. Assess and update the Business Case at the end of each stage
Answer: B
Explanation:
Explanation/Reference:
Organization Theme
Testlet 1
Scenario
Additional Information
Chief Executive Officer (CEO): He started the company 25 years ago and knows his job very well. He injured his leg two years ago which has restricted his visits to the engineering area. As CEO he has an overall perspective of the business strategic requirements and the authority to commit resources as required.
Marketing Director: She has been with the company for three years, following a successful career with a publicity company. She has the ability to represent the needs of the business, particularly as this is a marketing project. She has the authority to commit the annual business marketing budget, from which the project will be funded, as she sees appropriate. She will be responsible for monitoring the expected benefits of the calendar, in particular the improvement of the company's image.
Engineering Manager: He has been responsible for many engineering innovations in the company and is still as keen and energetic as the day he started. VVhilst he will not be part of the project team, his staff will feature in the photos for the promotional calendar.
Central Records: This group of five staff looks after all company records and document control. They now maintain all project files.
Bright Lights: This is the local office supplies company. It supplies all the stationery and office equipment needs of the company and will supply the stationery for this project.
Portraits ltd: This is a professional photographic company with a number of excellent photographers and a history of successful work. This company has been selected to take the photos for the company calendar. It has yet be decided which of the photographers to use.
NEW QUESTION 137
Additional Information
Chief Executive Officer (CEO): He started the company 25 years ago and knows his job very well. He injured his leg two years ago which has restricted his visits to the engineering area. As CEO he has an overall perspective of the business strategic requirements and the authority to commit resources as required.
Marketing Director: She has been with the company for three years, following a successful career with a publicity company. She has the ability to represent the needs of the business, particularly as this is a marketing project. She has the authority to commit the annual business marketing budget, from which the project will be funded, as she sees appropriate. She will be responsible for monitoring the expected benefits of the calendar, in particular the improvement of the company's image.
Engineering Manager: He has been responsible for many engineering innovations in the company and is still as keen and energetic as the day he started. VVhilst he will not be part of the project team, his staff will feature in the photos for the promotional calendar.
Central Records: This group of five staff looks after all company records and document control. They now maintain all project files.
Bright Lights: This is the local office supplies company. It supplies all the stationery and office equipment needs of the company and will supply the stationery for this project.
Portraits ltd: This is a professional photographic company with a number of excellent photographers and a history of successful work. This company has been selected to take the photos for the company calendar. It has yet be decided which of the photographers to use.
Which 2 statements explain why the CEO should be appointed as the Executive for this project?
- A. He knows his job very well.
- B. He has an overall perspective of the business's strategic requirements.
- C. He started the company 25 years ago.
- D. He has the authority to commit resources as required.
- E. He restricts his visits to the engineering area.
Answer: B,D
NEW QUESTION 138
Scenario
Product Summary
A list of customers will be collated. This will use existing information from the Accounts department about current customers, and existing information from the Marketing department about prospective customers.
Using the tariff of mailing costs available from the Post Office, a production cost forecast will be produced to allow the CEO and the Marketing Director to decide whether to continue with the project. If they decide to continue, they will give the approval to launch the internal label design competition. Competition rules will be required to communicate details of the competition to the staff. The chosen label design will then be selected from the competition entries.
The photos for the calendar must be based on existing photo design ideas available from the Marketing department. The selected photos will be chosen from these. Monthly calendar displays will be created to show the required layout of each page.
Product Breakdown Structure (contains errors)
Extract from Stage Plan for stage 3.
(All entries are true statements but may not be shown under the correct heading or in the correct document).
Using the Project Scenario and the Extract from Stage Plan for stage 3 provided as additional intonation for this question in the Scenario Booklet, answer the following 5 questions.
The Stage Plan for stage 3 has been produced.
The Engineering Manager insists that there are to be no interruptions to operations whilst photographs are being taken of the engineering staff performing their everyday duties and operating machinery. Two weeks ago the professional photographer produced the photo session schedule based on the operational staff schedule. The operational staff schedule is produced weekly and maintained by the Engineering Manager.
None of the £500 change budget has been used to date and this is available for the stage.
Which 2 statements apply to the External dependencies section?
- A. Move entry 5 to Plan description because the new company logo will be delivered during stage 3.
- B. Delete entry 7 because it should be shown in the Product Description for the label design.
- C. Delete entry 5 because the new company logo is being delivered by a separate project and will be detailed in the plans for that project.
- D. Move entry 5 to Plan prerequisites because the new company logo will influence the label designs.
- E. Delete entry 6 because the customer details were used in stage 2 to create the customer list.
Answer: B,E
NEW QUESTION 139
Project Scenario
Calendar Project (Note: The companies and people within the scenario are fictional.) There has been a reduction in fie number of orders at the MNO Manufacturing Company due in part to the increased marketing activities of its competitors. To help counter this, the company has decided to create a promotional calendar for next year for all its current and prospective customers. The end product of this project will be a prepared calendar pack, ready for printing. The design of the calendar will be similar to one sent out previously, and must reflect the company image as described in the existing corporate branding standards. Another project is currently producing a new company logo when is to be printed on each page of the promotional calendar. The prepared calendar pack will consist of:
Design for each month - correctly showing at public holidays and new company logo
Selected photographs- 12 professionally-produced photographs, showing different members of staff
Selected paper and selected envelope - for printing and mailing the calendar
Chosen label design - a competition to design a label will be held as part of this project
List of customers - names and addresses of customers to whom the calendar will be sent.
The project is currently in initiation and will have two further stages:
Stage 2 will include tie activities to:
Create the customer fast using information from the Accounts and Marketing departments
Confirm compliance with the Data Protection Legislation
Create a design for each month - this will be done by the internal creative team
Select and appoint a professional photographer
Gather photograph design ideas from previous project and agree photographic session schedule
Prepare a production cost forecast
Select paper and envelope.
Stage 3 will include the activities to:
Produce and select tie professionally-taken photographs
Hold the label design competition and choose the label design
Assemble the prepared calendar pack.
A production cost forecast, based on the options and costs for the paper, envelope, printing and marketing of the calendar is to be produced in stage 2. However, the actual production and distribution of the calendars is not within the scope of the project. The product cost forecast will be reviewed by the Project Board to determine whether tie project should continue.
It is now 05 October and the prepared calendar pack must be delivered to the print company by 30 November, to enable printing and distribution of the calendar in time for Christmas. The cost of the activities to develop the specialist products and the cost of the project management activities are estimated to be £20,000. There is a project time tolerance of +1 week /-2 weeks and a project cost tolerance of +
£6,000 / -£6,000. A change budget of £500 has been allocated but there is no risk budget.
During stage 2, an early review of the photo design ideas from the Marketing department has highlighted the need for engineering machinery to be operating in the background during the photo sessions. This requires a change to the baselined Product Description for the photos. What action should the Project Manager take?
- A. Include this requirement on the next Checkpoint Report to the photographer.
- B. Raise an Exception Report to the Project Board.
- C. Log the change in the Issue Register as a request for change.
- D. Revised the Product Description for the photos and issue it to the Engineering Manager to ensure that the machinery will be operating during the photo sessions.
Answer: C
NEW QUESTION 140
A construction company that is one of ABC Company's key clients has agreed to provide a member of the staff to review and comment on the 'e-learning course'.
Which stakeholder interest should the member of staff represent, and why?
- A. Supplier, because this stakeholder is an external supplier.
- B. Supplier, because this stakeholder provides the expertise required by the project.
- C. User, because this stakeholder may train its staff using the 'e-learning course'.
- D. User, because this stakeholder ensures that the project provides value for money.
Answer: D